Current reporting date is May 12th 2023
Acme Corp's project, which started on 2023-05-02 and is estimated to end on 2023-08-02, is currently in the green status, meaning it's progressing smoothly. Phase 1 of the project is completed (co), while phase 2 is ongoing (ot), with some deliverables verified (v) and others in-progress (i). Phase 3 is yet to start (bs). Feedback from the sponsor has been positive with a rating of 4.5, and the project manager, Guillermo, is appreciated for his cooperative nature.
Big Industries' project started on 2023-03-21 and is estimated to end on 2023-06-12. The status is orange, indicating some issues or delays. Phases 1 and 2 are completed (co), but Phase 3 is currently behind schedule (ot). The sponsor's feedback has been mixed with concerns about the project manager, Maria's, engagement. The last rating was 3.9.
Auto Motors' project started on 2023-04-04 and is estimated to end on 2023-07-12. The status is red, indicating significant issues or delays. Phase 1 is completed (co), but Phase 2 is behind schedule (bs). The sponsor's feedback indicates dissatisfaction with the deliverables and Ahmed's internal competition with his team, with the last rating being 3.5.
Cool Gadgets' project started on 2023-03-28 and is estimated to end on 2023-06-22. The status is orange. Phases 1, 2, and 3 are completed (co), but Phase 4 is behind schedule (bs). Feedback from the sponsor is mixed, with the latest rating being 4.2. Guillermo's neutrality is noted but is neither adding nor detracting value from the project.
Project Manager: Guillermo Blanco
Business Analyst: Maria Rodriguez
Developer: John Smith
Architect: Mia Patel
Interface Designer: David Nguyen
Security Manager: Olivia Brown
Support: Sophia Lee
Project Manager: Guillermo Blanco
Business Analyst: Maria Rodriguez
Developer: Emma Johnson
Architect: Mia Patel
Interface Designer: David Nguyen
Security Manager: Olivia Brown
Support: James Wilson
Project Manager: Guillermo Blanco
Business Analyst: Ahmed Khan
Developer: Pierre Dubois
Architect: Mia Patel
Interface Designer: David Nguyen
Security Manager: Olivia Brown
Support: Sophia Lee
Project Manager: Guillermo Blanco
Business Analyst: Maria Rodriguez
Developer: Hiroshi Nakamura
Architect: Mia Patel
Interface Designer: David Nguyen
Security Manager: Olivia Brown
Support: James Wilson
Requirements Analysis
Guillermo Blanco (PM): 30%
Maria Rodriguez (BA): 35%
Mia Patel (ARC): 20%
Data Integration
Guillermo Blanco (PM): 20%
John Smith (DEV): 40%
Mia Patel (ARC): 25%
David Nguyen (IFR): 15%
Olivia Brown (SEC): 15%
Configuration
Guillermo Blanco (PM): 25%
John Smith (DEV): 50%
Mia Patel (ARC): 35%
Maria Rodriguez (BA): 20%
Testing & Training
Guillermo Blanco (PM): 20%
John Smith (DEV): 30%
Mia Patel (ARC): 15%
Maria Rodriguez (BA): 30%
Sophia Lee (SUP): 30%
System Deployment
Guillermo Blanco (PM): 15%
John Smith (DEV): 15%
Mia Patel (ARC): 10%
David Nguyen (IFR): 20%
Olivia Brown (SEC): 20%
Sophia Lee (SUP): 20%
Requirements Analysis
Guillermo Blanco (PM): 30%
Maria Rodriguez (BA): 35%
Mia Patel (ARC): 20%
Data Integration
Guillermo Blanco (PM): 20%
Emma Johnson (DEV): 40%
Mia Patel (ARC): 25%
David Nguyen (IFR): 15%
Olivia Brown (SEC): 15%
Configuration
Guillermo Blanco (PM): 25%
Emma Johnson (DEV): 50%
Mia Patel (ARC): 35%
Maria Rodriguez (BA): 20%
Testing & Training
Guillermo Blanco (PM): 20%
Emma Johnson (DEV): 30%
Mia Patel (ARC): 15%
Maria Rodriguez (BA): 30%
James Wilson (SUP): 30%
System Deployment
Guillermo Blanco (PM): 15%
Emma Johnson (DEV): 15%
Mia Patel (ARC): 10%
David Nguyen (IFR): 20%
Olivia Brown (SEC): 20%
James Wilson (SUP): 20%
Requirements Analysis
Guillermo Blanco (PM): 30%
Ahmed Khan (BA): 35%
Mia Patel (ARC): 20%
Data Integration
Guillermo Blanco (PM): 20%
Pierre Dubois (DEV): 40%
Mia Patel (ARC): 25%
David Nguyen (IFR): 15%
Olivia Brown (SEC): 15%
Configuration
Guillermo Blanco (PM): 25%
Pierre Dubois (DEV): 50%
Mia Patel (ARC): 35%
Ahmed Khan (BA): 20%
Testing & Training
Guillermo Blanco (PM): 20%
Pierre Dubois (DEV): 30%
Mia Patel (ARC): 15%
Ahmed Khan (BA): 30%
Sophia Lee (SUP): 30%
System Deployment
Guillermo Blanco (PM): 15%
Pierre Dubois (DEV): 15%
Mia Patel (ARC): 10%
David Nguyen (IFR): 20%
Olivia Brown (SEC): 20%
Sophia Lee (SUP): 20%
Requirements Analysis
Guillermo Blanco (PM): 30%
Maria Rodriguez (BA): 35%
Mia Patel (ARC): 20%
Data Integration
Guillermo Blanco (PM): 20%
Hiroshi Nakamura (DEV): 40%
Mia Patel (ARC): 25%
David Nguyen (IFR): 15%
Olivia Brown (SEC): 15%
Configuration
Guillermo Blanco (PM): 25%
Hiroshi Nakamura (DEV): 50%
Mia Patel (ARC): 35%
Maria Rodriguez (BA): 20%
Testing & Training
Guillermo Blanco (PM): 20%
Hiroshi Nakamura (DEV): 30%
Mia Patel (ARC): 15%
Maria Rodriguez (BA): 30%
James Wilson (SUP): 30%
System Deployment
Guillermo Blanco (PM): 15%
Hiroshi Nakamura (DEV): 15%
Mia Patel (ARC): 10%
David Nguyen (IFR): 20%
Olivia Brown (SEC): 20%
James Wilson (SUP): 20%
This project has a high complexity and is set to start on 2023-08-01 with an estimated end date of 2023-11-07. The project is remote and the product to be delivered is the AI4PPM toolkit. The project is not started yet.
This project is of low complexity and is set to start on 2023-08-22 with an estimated end date of 2023-12-12. The project is remote and the product to be delivered is the AI4PPM toolkit. The project is not started yet.
This project has a medium complexity and is set to start on 2023-10-03 with an estimated end date of 2024-01-16. The project is remote and the product to be delivered is the AI4PPM toolkit. The project is not started yet.